15 free practice questions for the Project Management Professional (PMP) (PMP) exam, spread across the exam's domains. Try each one, then open the answer to see why every option is right or wrong.

  1. Question 1 · People

    During team chartering, an agile team agreed on ground rules, including that everyone joins the daily stand-up on time. One team member has now been late for several stand-ups in a row, and other members are getting frustrated. What should happen first?

    • ATeam members raise the lateness with the person directly, pointing to the ground rules everyone agreed to
    • BThe project manager privately warns the member that further lateness will be noted in their performance review
    • CThe project manager adds a new ground rule that sets a penalty for anyone who arrives late to the stand-up
    • DThe project manager escalates the attendance problem to the member's functional manager for corrective action
    Show answer and explanation

    Answer: A) Team members raise the lateness with the person directly, pointing to the ground rules everyone agreed to

    A team owns the ground rules it creates, so the first response to a breach is for members to hold each other accountable to that agreement. The project manager supports this and escalates only if needed.

    • ACorrect. The team wrote the ground rules, so it owns them. Members holding each other accountable to their own agreement is the first step, and the project manager supports and coaches as needed. Escalation comes only if the team can't resolve it.
    • BIncorrect. A private conversation is reasonable, but jumping straight to a performance-review threat makes this a disciplinary matter before the team has used its own agreement. It also moves accountability from the team to the PM.
    • CIncorrect. The team creates and changes its own ground rules. When the PM imposes a new rule alone, the team loses ownership, and the existing agreement hasn't been enforced yet.
    • DIncorrect. Escalation is premature. The team and PM should first try to resolve the issue using the team's own agreements, and escalate only if that fails.
  2. Question 2 · People

    A senior developer who owns a critical-path component tells the project manager privately that a family caregiving situation will limit them to reduced, variable hours for the next four weeks. A key integration milestone falls within that period. What should the project manager do first?

    • AMeet privately with the developer to understand their availability and agree a flexible working arrangement
    • BAsk the functional manager to assign a replacement developer for the four weeks to protect the milestone
    • CKeep the developer's assignments unchanged and log the capacity shortfall in the risk register as accepted
    • DShare the developer's situation at the next stand-up so the team can self-organize to cover the work
    Show answer and explanation

    Answer: A) Meet privately with the developer to understand their availability and agree a flexible working arrangement

    When a team member raises a personal difficulty, the project manager first talks with them privately to understand their constraints and agree a workable arrangement. Only then can the schedule impact be assessed accurately and handled while protecting confidentiality.

    • ACorrect. Empathy and servant leadership start with understanding the person's real constraints in private. Once a workable arrangement is agreed, the project manager can assess the milestone impact accurately and plan any redistribution without revealing private details.
    • BIncorrect. This is premature. It skips finding out what the developer can still contribute, may damage trust and engagement, and could lose critical knowledge when it is not necessary.
    • CIncorrect. This is passive. It neither supports the team member nor deals with a known threat to a critical-path milestone, and accepting the risk without analysis is not appropriate.
    • DIncorrect. Self-organization is a valid principle, but the developer shared the situation privately. Disclosing it without consent breaches confidentiality and damages trust.
  3. Question 3 · People

    A team member has the potential to grow into a lead role but lacks confidence and broader perspective. Over several months the PM meets with them regularly to share experience, discuss career direction, and give advice. What is the PM doing?

    • AMentoring — a longer-term, relationship-based development of the person's overall growth and perspective
    • BFacilitating a workshop
    • CPerforming a performance appraisal
    • DDirecting task execution
    Show answer and explanation

    Answer: A) Mentoring — a longer-term, relationship-based development of the person's overall growth and perspective

    • AMentoring focuses on the whole person and career over time. Coaching is more task- and performance-specific and time-bound; facilitating is guiding a group process toward an outcome.
    • BFacilitation is neutral guidance of a group's process, not one-on-one long-term development.
    • CAn appraisal is a periodic evaluation, not ongoing developmental support.
    • DTelling someone how to do a task is directing, not the developmental relationship described.
  4. Question 4 · People

    During the daily standup, a developer reports being blocked: the shared test environment has been down since yesterday, and the infrastructure team has not responded to the ticket. What should the project manager do next?

    • AContact the infrastructure team lead right after the standup and follow up until the environment is restored
    • BReassign the developer to unrelated backlog items and leave the ticket in the infrastructure team's queue
    • CExtend the standup so the whole team can discuss the outage in detail and agree on a workaround
    • DAdd the outage to the risk register and review it with stakeholders at the next scheduled risk review
    Show answer and explanation

    Answer: A) Contact the infrastructure team lead right after the standup and follow up until the environment is restored

    Removing impediments the team cannot clear itself is a core servant-leadership duty. The project manager follows up on blockers raised at the standup right away, instead of working around them, discussing them at length in the meeting, or putting them off.

    • ACorrect. The team cannot clear this blocker itself, so the project manager acts as a servant leader and uses their reach outside the team to get it removed. The standup brought the impediment to light, and the follow-up happens straight after it.
    • BIncorrect. Finding other work for the developer may help for a short time, but nobody is pushing to resolve the outage. The blocker stays in place and keeps slowing delivery.
    • CIncorrect. The daily standup is a short meeting for checking progress and spotting impediments, not for solving them. Detailed problem-solving should happen afterwards with only the people who are needed.
    • DIncorrect. The outage has already happened, so it is an issue to act on now, not a future risk. Waiting for the next scheduled review would make the delay longer.
  5. Question 5 · People

    An agile team lacks a skill it needs for work planned in the next iteration. Which approach best builds the team's long-term capability while keeping delivery on track?

    • AHave an experienced practitioner pair with team members on the work so the skill transfers during delivery
    • BBring in a contractor to complete that work this iteration while the team continues its current tasks
    • CSend one team member to a multi-week external course and defer the related work until they return
    • DAsk the most senior developer to research the skill alone and take ownership of all related work
    Show answer and explanation

    Answer: A) Have an experienced practitioner pair with team members on the work so the skill transfers during delivery

    Pairing an experienced practitioner with team members on real work transfers skills while delivering value. This builds a cross-functional team instead of creating dependencies or silos.

    • APairing delivers the current work and spreads the knowledge across the team. This increases cross-functionality and reduces future dependencies.
    • BThis delivers the work, but the knowledge leaves with the contractor. The team gains no capability and stays dependent on outside help.
    • CThis builds some skill, but it delays delivery and puts the knowledge in a single person, which creates a bottleneck.
    • DThis creates a knowledge silo and a single point of failure, and it leaves the rest of the team without the skill.
  6. Question 6 · Process

    Several versions of a technical specification circulate, and nobody knows which is current. Which practice solves this?

    • AConfiguration management
    • BResource leveling
    • CFast tracking
    • DEarned value analysis
    Show answer and explanation

    Answer: A) Configuration management

    • AConfiguration management controls versions and changes to project artifacts.
    • BLeveling adjusts schedules for resources.
    • CFast tracking overlaps activities.
    • DEVA measures performance.
  7. Question 7 · Process

    A supplier misses two consecutive status calls, which the risk register lists as a warning sign of delivery failure. What is this warning sign called?

    • AA risk trigger
    • BA secondary risk
    • CA residual risk
    • DAn issue log entry
    Show answer and explanation

    Answer: A) A risk trigger

    • ATriggers indicate a risk is about to occur or has occurred.
    • BSecondary risks arise from implementing responses.
    • CResidual risk remains after responses.
    • DAn issue is a current problem, not a warning sign.
  8. Question 8 · Process

    A product backlog holds far more items than the team can deliver in the near term, and every stakeholder insists their requests are top priority. How should the product owner and team proceed?

    • AHave the product owner order the backlog by value, risk, dependencies and cost of delay, using a technique such as MoSCoW
    • BRank items by the requesting stakeholder's seniority, placing executive requests ahead of the rest of the backlog
    • CGive each stakeholder an equal share of every iteration so all of their high-priority items progress in parallel
    • DHave the team estimate every item first, then deliver the smallest items first to maximize the number completed
    Show answer and explanation

    Answer: A) Have the product owner order the backlog by value, risk, dependencies and cost of delay, using a technique such as MoSCoW

    The product owner keeps a single ordered backlog based on value, risk, dependencies and cost of delay (for example, using MoSCoW), so the highest-value work is delivered first.

    • AOne ordered backlog based on relative value and factors such as risk, dependencies and cost of delay means the most valuable items are delivered first. Lower-value work is deferred or dropped.
    • BSeniority is not a measure of value or urgency. Ordering by rank can deliver low-value work early while high-value items wait.
    • CSplitting capacity evenly increases work in progress and delays every outcome. It avoids prioritizing rather than maximizing value.
    • DItem size alone ignores value, risk and dependencies. Finishing many small, low-value items doesn't maximize the product's value.
  9. Question 9 · Process

    Resources are overallocated, but the project end date can't move. Which technique adjusts resource use only within available float?

    • AResource smoothing
    • BResource leveling
    • CCrashing
    • DFast tracking
    Show answer and explanation

    Answer: A) Resource smoothing

    • ASmoothing adjusts activities within float, so the critical path and end date don't change.
    • BLeveling can extend the schedule to resolve overallocation.
    • CCrashing adds resources to shorten duration.
    • DFast tracking overlaps activities.
  10. Question 10 · Process

    A non-critical-path activity with five days of total float slips by two days. What is the appropriate response?

    • ANote the slip, confirm the activity still has positive float and hasn't affected the critical path, and continue monitoring it
    • BImmediately crash the activity by adding resources
    • CDeclare the project delayed and inform the customer
    • DRe-baseline the whole schedule
    Show answer and explanation

    Answer: A) Note the slip, confirm the activity still has positive float and hasn't affected the critical path, and continue monitoring it

    • AA two-day slip against five days of float doesn't delay the project; the PM verifies the critical path is unaffected and watches the activity in case it slips further and consumes its float.
    • BSpending money to compress an activity that still has float is unnecessary.
    • CThe project end date hasn't moved; float absorbed the slip.
    • DA minor slip within available float doesn't warrant re-baselining.
  11. Question 11 · Process

    A risk that was identified with a contingency plan actually occurs. What should the project manager do?

    • AExecute the pre-approved contingency plan and update the risk register and reserves
    • BTreat it as a brand-new issue and start planning a response from scratch
    • CIgnore it since it was only a risk
    • DImmediately request management reserve without using the contingency
    Show answer and explanation

    Answer: A) Execute the pre-approved contingency plan and update the risk register and reserves

    • AWhen a risk trigger fires, the planned response is enacted, and the register and reserves are updated to reflect the change.
    • BA response was already prepared; re-planning wastes time during the event.
    • CA realized risk becomes an issue that needs action.
    • DContingency reserve exists for identified risks; management reserve is for the unforeseen.
  12. Question 12 · Business Environment

    The organization has published sustainability commitments. During design, the team must choose between Material A, which is cheaper up front but produces significant waste that needs disposal, and Material B, which costs about 4% more but is recyclable. The approved business case emphasizes cost control. What should the project manager do?

    • APresent both options to the sponsor with lifecycle cost, disposal and compliance impacts, and fit with the published commitments, so a decision can be made
    • BSelect Material A, because the approved business case identifies cost control as the project's primary measure of success
    • CSelect Material B and cover the extra cost from the contingency reserve, since sustainability commitments outrank the budget
    • DAsk the material supplier to choose the option, since the supplier has the deepest technical knowledge of both products
    Show answer and explanation

    Answer: A) Present both options to the sponsor with lifecycle cost, disposal and compliance impacts, and fit with the published commitments, so a decision can be made

    Under PMI's stewardship principle, the project manager weighs financial, social and environmental impacts, including organizational commitments, and brings a total-value analysis to the appropriate decision-maker. Upfront cost alone should not decide the choice.

    • AStewardship means considering financial, social and environmental impacts together. Showing the full total-value picture lets the appropriate decision-maker make an informed trade-off that reflects both the business case and the organization's commitments.
    • BLooking only at the upfront price ignores disposal costs, compliance and reputational risk, and the organization's stated commitments. These are all part of total value.
    • CThis makes a values trade-off without the sponsor and misuses contingency reserve, which is set aside for identified risks and not for discretionary scope or design choices.
    • DSuppliers can provide data, but a trade-off involving cost and organizational commitments is a decision for the organization's stakeholders, not something to hand off to a vendor.
  13. Question 13 · Business Environment

    A medical device project must meet a mandatory industry safety standard. Design work has not yet started. What should the project manager do first?

    • ACapture the standard's applicable clauses as project requirements and trace them through design, testing, and acceptance
    • BSchedule a dedicated compliance audit near the end of the project once deliverables are functionally complete
    • CRequest a regulatory waiver for any clauses that appear likely to increase project cost or duration
    • DAdd a contingency reserve to the budget to cover rework that later compliance findings may require
    Show answer and explanation

    Answer: A) Capture the standard's applicable clauses as project requirements and trace them through design, testing, and acceptance

    Mandatory standards should be identified early and recorded as requirements, built into the scope and design, and traced through verification to acceptance, rather than inspected or fixed late.

    • ACorrect. Treating compliance as a requirement puts it into the scope and WBS early, where it can be designed in and verified through traceability. Fixing it late is costly and risky.
    • BIncorrect. A late audit finds gaps only after design decisions are locked in, which leads to expensive rework. Compliance has to be built in, not just inspected at the end.
    • CIncorrect. The standard is mandatory. Seeking waivers before confirming which requirements apply, and planning to meet them, is not the right first step. Waivers are exceptional and rarely granted for cost reasons.
    • DIncorrect. A reserve funds the cost of non-compliance after the fact. It does nothing to make sure the deliverable meets the standard in the first place.
  14. Question 14 · Business Environment

    Which is the best description of organizational governance as it relates to a project?

    • AThe framework of authority, decision rights, escalation paths, and oversight through which the project is directed and controlled
    • BThe integrated plan that defines the scope, schedule, and cost baselines the team uses to execute and monitor the project work
    • CThe set of tools and techniques the project manager uses to track tasks, report status, and coordinate the team's daily work
    • DThe staffing approach that determines which functional managers release people to work on project activities and for how long
    Show answer and explanation

    Answer: A) The framework of authority, decision rights, escalation paths, and oversight through which the project is directed and controlled

    Project governance is the framework of authority, decision rights, escalation paths and oversight that directs and controls a project. It is separate from the plan, the tracking tools and staffing.

    • ACorrect. Governance sets who can decide what, at what thresholds issues are escalated and to whom, and how the project is held accountable to the organization.
    • BIncorrect. This describes the project management plan and its baselines. Governance sets the decision and oversight framework the plan operates within.
    • CIncorrect. These are project management and control tools. They support reporting to governance bodies but are not the governance framework itself.
    • DIncorrect. This is resource acquisition and management. It is not the organization's structure of authority, decision rights and oversight over the project.
  15. Question 15 · Business Environment

    A project will change how 300 claims staff process their daily work. Technical testing is complete, but the sponsor is worried that staff will keep using old workarounds after go-live. What should the project manager do to best increase lasting adoption of the new process?

    • APlan structured change management that engages staff early, addresses resistance, and reinforces the change after go-live
    • BRun additional user acceptance testing cycles to confirm the solution fully meets requirements
    • CAsk the sponsor to issue a directive retiring the old process on go-live day
    • DDeliver one comprehensive training session for all staff during the week before go-live
    Show answer and explanation

    Answer: A) Plan structured change management that engages staff early, addresses resistance, and reinforces the change after go-live

    Lasting adoption of a new way of working requires structured organizational change management. That means engaging impacted people, addressing resistance, preparing them and reinforcing the change. Testing, mandates or one-off training are not enough by themselves.

    • ACorrect. Organizational change management deals with the people side of change: building awareness and support, uncovering and resolving resistance, preparing people, and reinforcing new behaviors so the change lasts.
    • BIncorrect. More testing confirms that the solution works, but it does nothing about staff willingness or readiness to change how they work, which is the sponsor's concern.
    • CIncorrect. A top-down mandate may force compliance at first, but without engagement and support it often leads to resistance and workarounds rather than real adoption.
    • DIncorrect. Training is needed, but a single session on its own does not address resistance or reinforce the new behaviors after go-live, so adoption may fade.

Ready for a full PMP practice exam?

These are a sample from the CertRidge question bank. Full practice exams match the real exam's length, time limit and domain weights, with every answer explained.

Original questions written from the official exam guide. Not affiliated with PMI; never copied from the real exam.