PMP · 41% of the exam
Process practice questions
10 free Process questions for the Project Management Professional (PMP) (PMP) exam, each with the correct answer and an explanation for every option.
What this domain covers
The largest domain: delivering the project across predictive, agile and hybrid approaches, from scope and schedule to risk, quality and procurement.
- Exam weight
- 41%
- On a real exam
- ≈ 74 questions
- In our bank
- 252 questions
Topics that come up most
- Choosing a predictive, agile or hybrid approach
- Scope, schedule and budget management
- Risk identification and responses
- Quality and change control
- Procurement and project closure
How to study it
Know when each approach fits; many scenarios ask what the project manager should do given the team's chosen way of working.
Sample Process questions
Try each one before opening the answer. Original questions written to the official exam objectives.
Question 1
An agile team draws each step that a feature passes through, from the initial request to production release. For each step, it records the time spent actively working on the item versus the time the item sat in a queue or came back for rework. Which technique is the team using, and what is its main purpose?
- AValue stream mapping — to expose non-value-adding activity in the end-to-end process so it can be removed
- BCumulative flow diagram — to show how many work items sit in each workflow state over time
- CIshikawa diagram — to sort the possible causes of one specific problem into categories
- DMonte Carlo simulation — to forecast likely completion dates from the variability in estimates
Show answer and explanation
Answer: A) Value stream mapping — to expose non-value-adding activity in the end-to-end process so it can be removed
Value stream mapping shows every step of the end-to-end flow and separates value-adding time from waiting and rework, so waste can be removed. CFDs, fishbone diagrams and Monte Carlo simulation serve different purposes.
- AA value stream map is a lean tool. It shows every step of the current-state process, separating value-added time from non-value-added time such as queues and rework, so the team can remove waste and design a better future state.
- BA cumulative flow diagram plots the number of items in each state over time and can hint at bottlenecks. It does not map each process step or record active versus waiting time per step.
- CA cause-and-effect (fishbone) diagram looks for the root causes of a single problem. It does not model the steps of a delivery process from start to finish.
- DMonte Carlo simulation models uncertainty to produce probabilistic forecasts. It does not map process steps or identify waste.
Question 2
The team needs an objective way to check whether a deliverable meets quality expectations, such as defect density limits. What should be defined?
- AQuality metrics
- BA product roadmap
- CA resource calendar
- DA team charter
Show answer and explanation
Answer: A) Quality metrics
- AQuality metrics define measurable attributes and how they'll be assessed.
- BThe roadmap shows planned capabilities.
- CThat shows availability; that doesn't meet this requirement.
- DThe charter covers team agreements.
Question 3
After a mitigation response, some risk remains that the team decides to accept. What is this remaining risk called?
- AResidual risk
- BSecondary risk
- CTrigger risk
- DOverall project risk
Show answer and explanation
Answer: A) Residual risk
- AResidual risk is what remains after planned responses.
- BSecondary risks are caused by responses.
- CThat isn't a standard term.
- DOverall risk concerns the whole project.
Question 4
A sponsor asks the project manager to explain how the cost baseline used for earned value tracking relates to the total project budget. Which explanation is correct?
- AThe baseline is work package estimates plus contingency reserve; adding management reserve gives the budget
- BThe baseline is work package estimates plus both reserves; the budget equals the baseline
- CThe baseline is work package estimates only; adding both reserves gives the budget
- DThe baseline is work package estimates plus management reserve; adding contingency gives the budget
Show answer and explanation
Answer: A) The baseline is work package estimates plus contingency reserve; adding management reserve gives the budget
Cost baseline = work package cost estimates + contingency reserve, time-phased. Project budget = cost baseline + management reserve.
- ACorrect. The cost baseline is the approved, time-phased total of the work package estimates plus contingency reserves for identified risks. Management reserve sits outside the baseline, and baseline plus management reserve equals the total project budget.
- BIncorrect. Management reserve is excluded from the cost baseline. It becomes part of the baseline only when it is released through change control.
- CIncorrect. Contingency reserve for identified risks is part of the cost baseline. Only management reserve is added on top to form the budget.
- DIncorrect. This reverses the two reserves. Contingency reserve is inside the baseline, and management reserve for unknown risks is outside it.
Question 5
Midway through a firm-fixed-price contract, the buyer's sponsor asks the seller for an additional training module that is not in the statement of work. The seller is willing but worried about cost and schedule. What should the project manager do?
- AProcess a change request so price, schedule and scope are agreed and the contract is amended before work begins
- BHave the seller start the module now and settle the additional price during final contract closeout
- CTreat the module as included because a fixed-price contract covers whatever the buyer reasonably needs
- DPay for the module from management reserve and add it with an email confirmation to the seller
Show answer and explanation
Answer: A) Process a change request so price, schedule and scope are agreed and the contract is amended before work begins
Under a fixed-price contract, new scope is a contract change. It must be processed through change control and the contract formally amended with agreed price and schedule before the seller starts the work.
- ACorrect. Adding a deliverable changes the contract. It should go through contract change control so both parties agree in writing on the scope, price and schedule impacts before the seller does the work.
- BIncorrect. Authorizing work before the change is priced and agreed invites disputes and claims. Changes should be agreed and documented before work begins, not settled after the fact.
- CIncorrect. A fixed price covers the scope defined in the contract. Work outside the statement of work is a change and needs a negotiated contract modification.
- DIncorrect. Funding alone does not change the legal agreement, and an informal email skips the change control process both parties must follow to modify the contract.
Question 6
A project has a budget at completion (BAC) of 100,000. To date, earned value (EV) is 40,000 and actual cost (AC) is 50,000. The project manager expects the cost performance seen so far to continue for the rest of the project. What is the estimate at completion (EAC)?
- A125,000
- B110,000
- C80,000
- D75,000
Show answer and explanation
Answer: A) 125,000
When current cost performance is expected to continue, EAC = BAC ÷ CPI. Here CPI = 40,000 ÷ 50,000 = 0.8, so EAC = 100,000 ÷ 0.8 = 125,000.
- ACPI = EV ÷ AC = 40,000 ÷ 50,000 = 0.8. When current cost efficiency is expected to persist, EAC = BAC ÷ CPI = 100,000 ÷ 0.8 = 125,000.
- BThis is AC + (BAC − EV) = 50,000 + 60,000. That formula assumes the remaining work will be done at the budgeted rate, so past overruns are treated as one-off. The stem says current performance will continue.
- CThis is BAC × CPI. Multiplying by a CPI below 1.0 lowers the forecast, but a project that is over budget will cost more than BAC, not less.
- DThis is the estimate to complete (ETC) = (BAC − EV) ÷ CPI = 60,000 ÷ 0.8. It covers only the remaining work. Adding AC of 50,000 gives the EAC of 125,000.
Question 7
A team builds a decision tree for a component. Building it in-house costs $200,000, with a 40% chance of $100,000 in extra rework. Buying it costs $230,000, with a 10% chance of a $50,000 integration fix. Based on expected monetary value, which option should be chosen?
- ABuild, because its expected cost of $200,000 is the lowest of the two paths
- BBuy, because its expected cost of $280,000 includes the integration fix
- CBuy, because its expected cost of $235,000 is lower than the build path
- DBuild, because its expected cost of $240,000 is lower than the buy path
Show answer and explanation
Answer: C) Buy, because its expected cost of $235,000 is lower than the build path
A decision tree weights each outcome by its probability and adds the results to get each alternative's EMV. Here Buy ($235,000) has a lower expected cost than Build ($240,000).
- AThis uses only the base cost and leaves out the probability-weighted rework branch (0.4 × $100,000).
- BThis adds the full $50,000 impact instead of weighting it by its 10% probability. Under that same mistake, Build would also be overstated.
- CBuy = $230,000 + 0.1 × $50,000 = $235,000. Build = $200,000 + 0.4 × $100,000 = $240,000. Buy has the lower expected cost.
- D$240,000 is the correct EMV for Build, but it is higher than Buy's $235,000, so the comparison is wrong.
Question 8
An agile team's retrospectives produce many good improvement ideas, but a few iterations later the same problems keep coming back and few changes have actually been made. What should the team do?
- APick the one or two most impactful improvements, give each an owner, and add them to the next iteration's backlog
- BRecord every improvement idea in a shared log and review the full list again at the next retrospective
- CHave the project manager choose the improvements after each retrospective and assign them to team members
- DLengthen the retrospective timebox so the team can examine each idea in more depth before acting
Show answer and explanation
Answer: A) Pick the one or two most impactful improvements, give each an owner, and add them to the next iteration's backlog
Retrospectives lead to real change when the team commits to a few prioritized improvements with clear owners and plans them into the next iteration.
- ACorrect. Committing to a small number of high-impact, owned actions and putting them in the next iteration's plan makes the improvements visible and much more likely to happen, which matches the Scrum Guide's guidance on retrospectives.
- BIncorrect. A growing list without priorities or owners keeps the current pattern going, where ideas are discussed but not acted on.
- CIncorrect. Self-managing teams own their process improvements. Moving the decision to the project manager weakens ownership and commitment.
- DIncorrect. The team's problem is following through, not a lack of discussion. More time spent talking does not turn ideas into committed actions.
Question 9
Which document authorizes the project's existence and gives the project manager authority to apply organizational resources?
- AThe project charter
- BThe project management plan
- CThe lessons learned register
- DThe stakeholder register
Show answer and explanation
Answer: A) The project charter
- AThe charter, issued by a sponsor, formally authorizes the project and names the project manager and their authority level.
- BThe plan describes how the project will be executed; it does not authorize the project.
- CThat captures knowledge during and after the project.
- DThat records stakeholders and their attributes.
Question 10
During Control Procurements, the seller files a claim saying a buyer-requested change is outside the contracted scope. The buyer disagrees. The contract's dispute resolution clause provides for mediation and binding arbitration. What should the project manager pursue first?
- ADirect negotiation between the buyer and seller representatives to try to settle the claim
- BMediation with a neutral third party, as provided in the contract's dispute resolution clause
- CBinding arbitration, because the contract already names it as the agreed resolution method
- DApproval of the claim through integrated change control so that work can continue
Show answer and explanation
Answer: A) Direct negotiation between the buyer and seller representatives to try to settle the claim
Contested claims are first handled by negotiation between the parties. If that fails, they move to ADR such as mediation or arbitration, and litigation is the last resort.
- ANegotiation is the preferred first step for resolving a claim. It keeps the decision in the parties' hands and costs the least. If agreement is reached, the claim becomes an agreed change.
- BMediation is a form of alternative dispute resolution. It is used when direct negotiation between the parties has failed, not before negotiation is tried.
- CArbitration comes late in the sequence because the decision leaves the parties' control. The fact that the contract allows it does not make it the first step.
- DA claim is by definition a disputed change. Approving it unilaterally ignores the buyer's position. The parties must first reach agreement, normally through negotiation, before it can be processed as an approved change.
Process: FAQs
How much of the PMP exam is Process?
Process is 41% of the PMP exam by the official exam guide's weighting, which on a 180-question form works out to roughly 74 questions. The real exam's exact split varies by form.
What does the Process domain cover?
The largest domain: delivering the project across predictive, agile and hybrid approaches, from scope and schedule to risk, quality and procurement.
How should I study Process for PMP?
Know when each approach fits; many scenarios ask what the project manager should do given the team's chosen way of working.
Where can I practise more Process questions?
This page has 10 free Process questions with answers. CertRidge's PMP question bank has 252 questions in this domain. Every practice exam result breaks your score down by domain, and Review Mode re-drills the questions you missed.
Other PMP domains
Also: 15 free questions across all domains, the PMP cheat sheet and the study guide.
Get Process exam-ready
The full PMP bank has 252 Process questions. Timed practice exams match the real exam's length and domain weights, every result shows your score per domain, and Review Mode re-drills the questions you missed.
Not affiliated with PMI; questions are original and never copied from the real exam.